Project Details
Project: "CONSTRUCTION OF THE GROUP OF THIRD STATIONS"
Place: Aspropyrgos, Attica
Budget: 49,000,000.00 €
Contractor: TECHNICAL OLYMPIC S.A.
Subcontractor: PYRAMIS S.A.
Value of executed works: 1.693.283,00 €
Place: Aspropyrgos, Attica
Budget: 49,000,000.00 €
Contractor: TECHNICAL OLYMPIC S.A.
Subcontractor: PYRAMIS S.A.
Value of executed works: 1.693.283,00 €
Project Overview
The project concerns the construction of the road network and the 280 parking spaces. They consist of:
- The New North Ring Road, 3.5 km long
- The Main Internal Road 4.5 km long
- Smaller roads totaling 500 meters in length
- EC parking and storage areas with a total area of 200.000 sqm.