Project Details
Project: PATHE Section Skarfeia-Lamia-Raches «Subsection Skarfeia(OSE Bridge) to I/C Thermopylon»
Location: Maliakos (Central Greece)
Budget: 49.000.000,00€
Contractor: J/V EUROIONIA
Subcontractor: PYRAMIS SA
Value of executed works: 1.100.000,00€
Location: Maliakos (Central Greece)
Budget: 49.000.000,00€
Contractor: J/V EUROIONIA
Subcontractor: PYRAMIS SA
Value of executed works: 1.100.000,00€
Project Overview
The project concerns the construction of a section of PATHE-Corridor X.
Specifically concerns the construction of the motorway main alignment with a total length of approximately 17,4 km with a cross section comprising of two lanes and an emergency lane per direction and a central island of 4,5 m wide. As far as the carriageway is concerned, the highway follows in several sections the existing National Road with one-sided widening and bypasses the Molos and Thermopyles areas.